1:05PM Incredibly convoluted testimony. In essence, Rataj tried to demonstrate that this wasn't a low bid contract process and there was no requirement to take lowest bidders. Also that DLZ, the construction management company for the umbrella contracts, had issues with not having appropriate performance bonds.

The last point Rataj made, in reference to yesterday's series of change orders on Ferguson contracts, was that it was not unusual for contractors to issue them. Case in point Lanzo Construction which had 12 change orders and L.D'Agostini with 8 under umbrella contract CM 2012.

Court resumes tomorrow at 9AM.

About the author:

Alexandra Harland is a Princeton undergrad and has a masters degree in International affairs with Columbia. A Montreal native, she worked with the Daily Telegraph newspaper for a few years before transitioning to TV, when she worked at ABC News with Peter Jennings. Alexandra has also worked in newsrooms in both Detroit and Boston.