Asks about revenues? I don't know says witness.

L D'agostini had at least 8 change orders? Yes.

Went from $1.3 million to $5.4 million? Yes.

Lanzo had 12 change orders at least. Do you know how many they had total? No.

Went from $1.4 million to $6.4 million? correct.

WS 657 $1.5 million for McCormick how many change orders do you know? no sitting here no.

Do you know revenue total on 657? No I do not.

Rataj says he's done. but consults with Gerald Evelyn and comes back with more questions.

Rataj puts up document that says WS 650 ended up with $3.1 million and not $3.4 million as witness testified yesterday.

Witness says she reconciled all documents.

Rataj says where is the document? Witness says it has been produced and will be introduced in my later testimony.

Looking at contract 651- the document Rataj puts up says that the contract was ultimately $1.7 million instead of the $3.5 million she testified yesterday.

Yes that's what it says.

Rataj is done with witness. And she is so done with him.

11:45AM Jim Thomas, Kwame's lawyer, cross examines.

Talking about special administratorship and the orders that go with that.

You testified yesterday that Kilpatrick signed 2012? Yes says witness.

Do you remember telling jury that it was signed and approved by the mayor? Yes.

You understand that CM 2012 wasn't signed till 2004? Witness says that she would have to see signature page to verify that.

Special Administrative Order 2003-3. document from special administrator to City Council? Amongst others, yes says witness.

This is an award for construction management to DLZ? Yes.

Signature date is 6/28//03? Yes.

Do i have to go through with you the 2003 DLZ emails that go towards awarding contract? No.

Special administratorship appointed way before Kilpatrick was? Yes.

Amendment to special administrator order when Kilpatrick was elected? Yes.