"All other avenues had failed so I had nothing to lose by going to Bobby," said the witness.

In December 2004, Lakeshore teamed with Ferguson and Lanzo Lining to submit a bid proposal for a $20 million DWSD water contract. They agreed that if they got the contract, they would split the profits 3 ways.

The team was awarded the contract, WS 849, on March 24th, 2005 and was advised by DWSD that they could begin work immediately. Angelo D'Alessandro, Lanzo head, and Ferguson were at odds on how to breakdown the work. Both wanted to take the same line items. D'Alessandro approached Ferguson with a figure of $400,000 to $500,000 just to let Lanzo have the work. Ferguson refused saying he could make more money. Ferguson was ultimately offered more than $1 million  to walk away from the job.

In September 2005, Hardiman approached Ferguson about two change orders they wanted. One was for an additional $6 to $8 million on contract 849 and the other was for an asbestos contract for $1.5 million. Hardiman explained that he knew that Ferguson had the necessary city relationships and wanted to ensure his company wasn't blind-sided like with the two cancelled contracts.

Ferguson agreed to help with the change orders but charged 5% on the contract orders for levying his contacts. His total take on the change orders was $450,000 including $25,000 cash that a panicked Hardiman rushed to Ferguson's offices.

"I did not want to upset Bobby Ferguson," explained Hardiman.

Some time later, Lakeshore Engineering and various partners won DWSD water contract 2014. Ferguson approached Hardiman at his offices and told him that he needed to include his company Xcel Construction on the project. When the witness asked why, Ferguson simply said "because they need to help you out." Despite balking at Ferguson's initial request for $400,000 for doing nothing, Hardiman said he caved because he was still haunted by the lost contracts.

Hardiman recounted how Ferguson's associate Calvin Hall would come to his offices, sit in on meetings and request payment. "You're a parasite," Hardiman said he would tell a mild-mannered Hall.

In the period between January 1st 2007 and November 10th 2011, Hardiman's A & H Contractors paid Xcel contruction more than $620,000.

When a change order came up on contract 2014 to do more work on 7 streets in an east side development that should have gone to A & H Contractors, the witness testified that Ferguson nudged his way into the deal walking away with 4 streets and leaving A & H with the remaining 3. And for that, Ferguson Enterprises was paid $1,437,304.73.

Finally, Hardiman talked about Ferguson's shenanigans on water contract 865. Lakeshore Engineering along with D'Alessandro Contracting and others submitted a bid proposal for the contract for sewer repairs on the east side of Detroit. They had asked Ferguson to join but he was already with Inland's team. When Lakeshore was awarded the grant, however, Ferguson wanted in.

Hardiman testified to receiving a call while he was out-of-town by an upset D'Alessandro who told him that Ferguson was on his site and demanding that he leave. Hardiman asked Ferguson to let D'Alessandro complete the work but Ferguson staunchly refused. Hardiman ended up asking D'Alessandro to stop to let Ferguson take over.

US attorney Mark Chutkow asked the witness what Ferguson said he'd do if he didn't get D'Alessandro off the job site.

"I will shut these effin jobs down."

And Hardiman knew from experience that was a promise Ferguson was in a position to make good on.

About the author:

Alexandra Harland is a Princeton undergrad and has a masters degree in International affairs with Columbia. A Montreal native, she worked with the Daily Telegraph newspaper for a few years before transitioning to TV, when she worked at ABC News with Peter Jennings. Alexandra has also worked in newsrooms in both Detroit and Boston.