The eastbound and westbound M-59 (Hall Road) ramps to southbound M-53 will also be closed.
Southbound M-53 traffic will be detoured via westbound M-59 (Hall Road) to southbound Mound Road, then eastbound 18 Mile Road to southbound M-53.
There will also be local road closures for bridge work on M-53 at the following intersections:
Utica Road,
19 Mile Road, and
Canal Road.
This work is part of a $16 million project on M-53 (Van Dyke Freeway) between 18 Mile Road and M-59 (Hall Road) to resurface the roadway, perform concrete and guardrail repairs, repairs to 10 bridges, and resurfacing the 23 Mile Road ramps to M-53. Based on economic modeling, this investment is expected to directly and indirectly supports 227 jobs.